Single Line Working Between Anand Vihar and Vaishali Section of Line-4


Delhi Metro train services between Anand Vihar and Vaishali section of Line-4 (Yamuna Bank - Vaishali) will be run on single line today (13th January 2012) from 11:00 AM to 03:00 PM, owing to maintenance work. As a result of this, headway of 13 min will be maintained during this period between Anand Vihar and Vaishali section instead of the routine headway of 5 min 12 sec. Normal train services will resume after 3:00 PM on this section.

However, services will run as per normal schedule on rest of the sections of Line-4 i.e, between Anand Vihar and Yamuna Bank and all other lines of the Delhi Metro network.


AD/CPRO/DMRC      << Back
#
#