Majlis Park - Shiv Vihar

Length 58.596 km out of which 39.479 km is Elevated and 19.117 km is Uderground. Total 38 stations out of which 26 are Elevated and 12 are Underground. Progress of civil works upto February 2019 is 99.50 percent. The line has been opened in stages by 31.12.2018.(Except Trilokpuri to Mayur Vihar Pkt-1 section due to land issue at Trilokpuri)
 